Sidewalk Program 2017

Sidewalk Program
Location:  1) Thomas Street/Sundown Trail at Summercrest Blvd
2) Market Street: From Thomas Street to existing sidewalks
3) Gardens Blvd: From Bailey Lake Park to Tena Court
Start Date:
Projected start date - September 15, 2017
End Date: 
December 2017 
Purpose: To fill in missing sidewalk portions in the city. 
End Result:
Providing sidewalk connections for increase pedestrian/cyclist mobility and safe routes to school throughout the city. 
Project Cost: $80,000
Funding Source: 
Street Bond Funds - Annual Sidewalk Program
Progress:  Project completed November 2017.
Closures/Detours:  Project complete.