15” Sewer Extension of Quil Miller Line– Business Park

HighPoint Business Park Sewer Line
Location:  Quil Miller Creek in the Highpoint Business Park area, IH35W at Highpoint Boulevard
Approximate
Start Date:
July 2018
Approximate 
End Date: 
December 2018
Purpose: To provide sewer service to future development in the business park and areas beyond.    
End Result:
Sewer service is adequate for existing development and in place to serve future development.    
Project Cost: $800,000
Funding Source: 
Sewer Bond Funds

Progress:  Project has been advertised for bid.
Closures/Detours:  None expected. Work is generally in the creek area.