Location: | Prairie Timber Park, 801 Prairie Timber Rd |
Approximate Start Date: |
Summer 2020 |
Approximate End Date: |
2021 |
Description: | Evaluation and correction of drainage problems cause by situation on an extremely flat site; correct conditions that cause a portion of the walking trail around the pond to become submerged after heavy rain events. |
Project Cost: | $300,000 |
Funding Source: | Park Improvement Fund (353 Gas) |
Approval Date: | November 6, 2017 |
Progress: | June 2019: redesign is currently underway. |