Hidden Creek Parkway Traffic Signals

Hidden creek parkway intersection lights
Location:  Traffic signals will be installed at the intersections of:
- Hidden Creek Parkway and Hurst Road
- Hidden Creek Parkway and Cardinal Ridge Road
- Hidden Creek Parkway and Arrowwood
- Hidden Creek Parkway and Hidden Vistas (future signal)
Approximate
Start Date:
April 2019: Construction has begun.
Approximate 
End Date: 
June/July 2019 
Purpose:
For improved safety and traffic flow as Burleson ISD's new Kerr Middle School opens off of Hidden Creek Parkway. 
End Result:
The project includes traffic signals at three intersections along Hidden Creek Parkway. 
Project Cost: Estimated $600,000
Funding Source: 
Street Bond Fund, Burleson ISD is funding the signal at Arrowwood intersection. 

Progress: 
- March 2019 - project awarded to Bean Electrical.
- April 2019: installation of traffic signal at Hidden Creek Parkway and Hurst Road has begun. 
Closures/Detours:  To be determined, minimal traffic disruption expected.