A sign will be placed near the proposed well site advising that a permit application has been submitted. Notices will be sent to residents / property owners within 1,000 feet of the well site. Additionally, staff sends a separate notice to residents/property owners if a proposed well is to be located within 1,000 feet of any protected use.
A pad generally 300 feet by 300 feet will be prepared and a drilling rig will move onto the location. The drilling rig will be on site for approximately 20-30 days actually “drilling” the well and running pipe into the open hole. After the well is drilled the drilling rig will move off. The rig move and drilling is a 24 hour operation and is probably the noisiest part of the operation. Shortly thereafter, well “completion” will begin and a smaller portable rig will move onto the location.
After completion operations, surface equipment will be installed along with appropriate fencing and gates. From this point there will be minimal activity on the location. Occasionally a small rig will be brought to the location for remedial work.